2018 Classroom Technology Renewal

Photo of instructor station for 2018 technology renewal
Photo of instructor station for 2018 technology renewal

The Office of Classroom Management (OCM) is committed to providing instructional technology in general purpose classrooms. Scheduled technology equipment lifecycle updates each year minimize breakdowns and maintain functionality. 

In 2018, nearly 70 rooms are scheduled to receive updated classroom equipment. Improvements include wide-screen video projectors, HDMI cable with attached Mini-DisplayPort adapter, USB-C cable, and upgraded control systems. Each of the classrooms also receive a general tune-up of all related technology components.

East Bank: 

  • 10 Church St Auditorium (Formerly Bell Auditorium)
  • Amundson B75
  • Bruininks 114, 117, 119, 121, 123, 144, 131A & 131B, 412, 420A & 420B, 432A & 432B*, 512A & 512B, 530A & 530B
  • Ford Hall 115, 151, 155
  • Keller Hall 3-230
  • MCBB 2-120, 2-122
  • Murphy 130
  • Peik Gym G65
  • Peik Hall 335, 375
  • Rapson Hall 43, 45, 58, 100

*These rooms will be combined

West Bank:

  • Blegen 440
  • CSOM 1-147, 1-149
  • HHH 15, 35, 60, 184
  • Social Sciences 278
  • West Bank Auditorium 20

St. Paul: 

  • Bio Sci 12
  • Borlaug 335
  • Borlaug 365
  • Haecker 205
  • Peters 155
  • Ruttan B22, B26, B30, B35, B36

The technology update project for this year started in January and should be completed in September 2018.


Timeline:
-
Project Phase:
Campus: